Parks Highway Area Projects : South Mack Drive Connection : SCHEDULE


Project scoping, environmental research and field investigations, preliminary engineering, surveying, and permitting are underway. 

South Mack Drive Extension Schedule Graphic


Environmental Analyses — April 2009-November 2009
Permitting — April 2009-April 2010
Preliminary Engineering Report — April 2009-January, 2010
Public Involvement — April 2009-April 2010