The Matanuska-Susitna Borough received funds to design and construct the Museum Drive and the Machen Road extensions in 2008. In May 2009, HDL received the go-ahead to begin design and produce bid-ready plans by late 2010. Construction could begin as early as 2011.

Begin project - May 2009
Environmental - May 2009 through February 2010
Surveying - June 2009 through July 2009
Geotechnical Investigation - July 2009 (15 days)
Traffic and Safety Analysis - June 2009 through July 2009
Design Study Report - September 2009 through mid-December 2009
Right of Way Mapping - August 2009 through April 2010
Right of Way Acquisition - April 2010 through end of design September 2012
Utilities - September 2009 through September 2012
Plans, Specification and Estimates - August 2009 through September 2012
Bidding & Construction Contract Award - September 2012 through beginning of construction 2013
Construction is anticipated in 2013
Public Involvement - May 2009 through beginning of construction 2013
|